— Advertisement —

Dexter paving two weeks behind schedule, but ready to Bike to Work Day

Note: Phase dates have not yet been adjusted for the project delays

Due to rainy and cold weather, Dexter Ave N construction is running about two weeks behind schedule. However, the contractor still expects to complete the project by October.

As Bike to Work Day nears (Friday), the first phase of Dexter Ave N paving has been completed. Crews are now working to stripe the new buffered bike lanes and install the concrete bus islands for the northern third of the project (see our previous story for more project details).

The second phase of repaving (which involves grinding away pavement, lane closures, etc all over again) is scheduled to start next week, ever so conveniently avoiding the thousands of extra people expected to ride to work for Bike to Work Week.


— Advertisement —

Josh Stepherson of Stepherson & Associates, which is helping to manage the project, wants to know what you all think of the project so far. If you have been avoiding Dexter the past couple months, give it a try this week and be sure to leave a comment here with your thoughts.

From Stepherson:

Phase one paving was initially planned for April 25th & 26th, unfortunately, due to poor weather conditions (paving requires 24 hours without rain and temperatures in excess of 40 degrees), the contractor was not able to complete paving until May 10th.

Now that paving has been completed, the contractor is able to finish the remaining work in phase one.  This includes building transit islands, inserting a buffered bike lane and applying permanent street channelization.  Phase two construction is scheduled to begin the week of May 23rd.

Though the completion date for phase one is a couple of weeks later than initially planned the contractor is still planning to complete its work in October.


About the author:


Related posts:

Comments

One response to “Dexter paving two weeks behind schedule, but ready to Bike to Work Day”

  1. Chris Hennessy

    I am very curious why the first stretch of dexter needs to be completed before crews can start grinding off the pavement on the next section. It seems to me that the grinding and preparation take a couple weeks-and can be done in the rain-so if they had done that when they were unable to do the paving-they would be that much further ahead once the first section was paved. Sort of a leapfrog approach-the work on the second section starts before the first section is done-

— Advertisement —

Join the Seattle Bike Blog Supporters

As a supporter, you help power independent bike news in the Seattle area. Please consider supporting the site financially starting at $5 per month:


Latest stories

Bike Events Calendar

May
4
Sat
9:00 am First Saturday Neighborhood Clea…
First Saturday Neighborhood Clea…
May 4 @ 9:00 am – 12:00 pm
Every month volunteers gather to collect garbage and help beautify our neighborhood. On average, we collect about 15 bags of garbage per clean up, which means 1,000’s of small pieces of plastic that do not[…]
May
7
Tue
6:30 pm West Seattle Bike Connections mo… @ Online
West Seattle Bike Connections mo… @ Online
May 7 @ 6:30 pm – 8:00 pm
 ShareMastodonTwitterFacebookRedditEmail
May
8
Wed
6:00 pm Monthly SPAB Meeting @ Virtual meeting
Monthly SPAB Meeting @ Virtual meeting
May 8 @ 6:00 pm – 8:00 pm
http://www.seattle.gov/spab/ShareMastodonTwitterFacebookRedditEmail
May
9
Thu
4:45 pm Fix the Burke-GIlman Advocacy Ride @ Seattle Parks and Recreation Bldg
Fix the Burke-GIlman Advocacy Ride @ Seattle Parks and Recreation Bldg
May 9 @ 4:45 pm – 8:00 pm
There is going to be an advocacy ride to the Board of Park and Recreation Commissioners meeting at 6:30 pm on Thursday, May 9th. The goal is to get as many bicyclists as possible to[…]
7:15 pm Point83 @ Westlake Park
Point83 @ Westlake Park
May 9 @ 7:15 pm
Point83 @ Westlake Park
Meet up in the center of the park at 7ish. Leave at 730. Every Thursday from now until forever rain or shine. Bikes, beers, illegal firepits, nachos, bottlerockets, timetraveling, lollygagging, mechanicals, good times.ShareMastodonTwitterFacebookRedditEmail
— Advertisements —

Latest on Mastodon

Loading Mastodon feed…